Have you seen a nuclear bomb? Well not quite, but let's not sugar coat it...pool construction is a major undertaking and is going make a mess in your backyard for the 5-10 days it takes to install a Viking Pool. There is no clean way to excavate 100 tons of soil, bring in 50 tons of sand, dig plumbing & electrical trenches, crane the pool into place, pour 30 yards of concrete sub-deck and then install 20 tons of flagstone decking.

Project schedules are based on scope of work but our basic process involves the following:
Day 1 - Pool Excavation - Sand Delivery - Equipment Delivery
Day 2 - Pool Base installation - Sand Staging - Equipment Set
Day 3 - Run plumbing from equipment to pool side - Pool Shell Installation w/ crane - Electrical hook-up - Plumb pool - Start pool filling / backfilling
Day 4 - Continue backfilling and pool filling
Day 5 - Layout and Form Deck
Day 6 - Required Inspections - Permanent Fence
Day 7 - Pour Deck - Finish Fence if required
Day 8 - Strip concrete forms - final grading
Day 9 - Landscaping
Day 10 - Final Inspection - Enjoy your new pool